Idle reason:
According to the new plant planing , we have to move to our new plant in another industry park and have installed new production line. So we want to transfer this well running production line.
Running status:
This production was installed in 8-9, 2005. All the parts of this line are running well and can individually running. The whole machine had been reformed to the hanging, water balance and electric control parts in July, 2008, the running status is greatly improved.
Technical specification
Main machine:
¢65 plastic extruder SPV 65/20F
¢150 plastic extruder SPV 150/25
¢90 plastic extruder SPV 90/20F
All these extruders are equipped with STF series hopper type dryer and automatic feeding machine
Hauling:
Upper hauling: Belting hauling machine BQ20D(F)(2m capstan)
Down hauling: caterpilar LQ3C
Accumulator, pay-off and take-up device:
Accumulator: 1set
accumulating length(120m) wire clamper is included
¢1600~2000 portal type travaling pay-off: 1set
¢1600~2500 portal type travaling take-up: 1set
Heating section: 6 sections about 43m
Cooling section: 8 sections about 50.5m
heat insulation section: 3 sections about 12.1m
Pay-off dancer 1 set
Hanging machine and water vapour balancer:
Overhang controller
water vapour balancer (reformed)
up and down sealer
Extruder head oil heating (2 sets oil heater)
Online detecting device:
ZUMBACH derivometer 1 set(1 set of accessories made in China)
Electric control part:
Siemens PLC controller Hitech touching screen Mitsubishi transducer
|